Eastern Shipbuilding Group began construction on three new hybrid-electric ferries for Washington State Ferries on August 5, 2026, marking the first new ferry construction in a decade. The state exercised an option to add a third vessel to the contract with Eastern, which had already been selected over a Washington-based bidder for its 30% lower bid.
The $714. 5 million contract for three ferries saves taxpayers $360 million compared to the alternative bid, with total costs including additional expenses at $1. 15 billion. The ferries will replace aging vessels, as Washington's ferry system has declined from 25 vessels in 2015 to 21 in 2025, needing 26 for effective operation. Governor Ferguson noted the ferries are essential for island communities and tourism, including moving World Cup travelers.
The new ferries, set to be delivered in 2028, will improve reliability and reduce emissions. The governor plans to use savings from the contract to fund a fourth ferry, with the state legislature having appropriated $1. 3 billion for the project.